The Board of Directors of Unipro PJSC Held a Meeting

On 7 August 2017 the Board of Directors of Unipro PJSC held a meeting in absentia. The agenda covered the issue of updating the parameters of Investment Project “Repair of Power Unit No. 3 of Berezovskaya GRES Branch of Unipro PJSC”.

The Board of Directors of Unipro resolved to change the key indicators of “Repair and Recovery of Power Unit No. 3 of Berezovskaya GRES” project in terms of costs and implementation deadlines.

The Board of Directors members approved increasing the costs of repair of Power Unit No. 3 of Berezovskaya GRES. About 11 billion roubles (including 8 bn roubles capitalized expenses) have been spent for the repair of the power unit as of 30 June 2017. Further repair of the power unit will cost about 28 billion roubles.

According to the current estimates, Unipro PJSC expects to start receiving payments for the Berezovskaya GRES Power Unit No. 3 capacity under CSA in the third quarter of 2019.